Quick reference · Fire detection and alarm systems in non-domestic premises
BS 5839-1: quick reference
How to design, install, commission and maintain fire detection and fire alarm systems in buildings other than homes: where detectors and call points go, how loud the alarm must be, how the system is tested and serviced, and what is recorded.
The rulebook for fire alarms in shops, offices, factories and other non-domestic buildings: where to put detectors and call points, how loud the alarm has to be, and how the system is tested and looked after.
2025. BS 5839-1:2025 replaced the 2017 edition in April 2025.
Confirmed two or more sources agree, or a source quotes the standard. Check one source, or a detail that could not be confirmed. Check it against the standard.
Every point in a protected area should be within 7.5 m horizontally of a smoke or CO detector, or 5.3 m of a heat detector. Laid out on a square grid, that is about 10.6 m between smoke detectors and 7.5 m between heat detectors. The figures are unchanged from 2017.
A smoke detector looks after everything within 7.5 m of it. A heat detector looks after everything within 5.3 m. Space them so that nowhere is further away than that.
Nowhere should be more than 7.5 m from a smoke detector or 5.3 m from a heat detector. The dashed square is the biggest square one detector covers, which is what sets the spacing on a grid.
Point smoke and CO detectors: 10.5 m, or 12.5 m over up to 10% of the area. Heat detectors class A1: 9 m (10.5 m for 10%). Other heat classes: 7.5 m (10.5 m for 10%). A multi-sensor that works on heat and smoke only takes the heat limit.
Smoke detectors work up to 10.5 m high. The better class of heat detector works up to 9 m, and the others up to 7.5 m. Up to 10% of the area can be a bit higher.
The normal limit is the green part. Over up to 10% of the area a detector may go a little higher, up to the top of the brass part.
In a corridor under 2 m wide the coverage areas do not need to overlap, so smoke detectors can be about 15 m apart and heat detectors about 10.6 m. A corridor wider than 2 m is treated as a room.
In a corridor narrower than 2 m, detectors can be further apart: about 15 m for smoke and about 10.6 m for heat. Wider than 2 m, treat it like a room.
In a corridor under 2 m wide the coverage circles do not need to overlap: about 15 m apart for smoke and 10.6 m for heat. Wider than 2 m, space detectors as in a room.
A ceiling counts as flat if its apex is under 150 mm above the eaves for heat detection, or under 600 mm for smoke (clause 21.2.2). Above that, a detector goes at or near the apex, and its radius alone can grow by 1% for each degree of roof pitch, up to a maximum of 25% (clause 21.2.3).
A slight slope is treated as flat. Steeper than that, put a detector at the top, and it can cover a little further out.
A slight slope counts as flat. On a steeper roof put a detector at the apex, and its radius alone can grow.
At least 65 dB(A), or 5 dB(A) above any background noise that lasts more than 30 seconds, whichever is higher, with the doors closed. In sleeping areas the level is 75 dB(A) at the bed head. In stairways or enclosures under 60 m² (not corridors) it can be 60 dB(A).
Everywhere should hear the alarm at 65 dB(A) or more, or 5 louder than the background noise if that is higher. At a bed head it should be 75 dB(A). In small stairways and enclosures 60 is enough.
Measure with the doors closed. A normal door takes off about 20 dB(A) and a fire door about 30.
Annex C gives typical background noise ranges by building type and area — for example airport terminals, courtrooms, factories and offices — as an informative guide only, since noise varies a great deal between buildings of the same type and even within the same building. Where the table is used, the higher figure in the given range should be taken, and a real on-site measurement is always preferred over the table (clause 15.1.3 Note 2, Annex C).
There is a reference table (Annex C) of typical background noise levels by building type, to help work out if the fire alarm needs to be louder than the standard 65 dB(A) minimum. It is only a guide — noise varies a lot even within the same type of building — so use the higher end of any range given, and measure on site for real whenever you can.
As a rough guide, a normal door cuts the sound by about 20 dB(A) and a fire door by about 30 dB(A). The real test is a measurement with the doors shut.
A normal door takes about 20 dB(A) off the sound and a fire door about 30. Always measure with the doors closed.
A zone should not be larger than 2,000 m² of floor area, whether its detectors are addressable or not (clauses 12.2 to 12.4). The one exception is a zone that is mainly one open-plan area, such as an uncompartmented warehouse, which can go up to 10,000 m². A zone normally covers one storey, and stairways and lift shafts are separate zones.
One zone should normally cover no more than 2,000 m² of floor, and one storey, whether or not the detectors are addressable. A single big open area like a warehouse can be larger, up to 10,000 m². Stairs and lift shafts get their own zones.
A zone is up to 2,000 m² of one storey. Stairways and lift shafts are zones of their own.
A detection zone is about locating a fire on the panel; an alarm zone is about which sounders operate together. Every alarm zone boundary (other than an external wall) must be fire-resisting construction, since occupants in one alarm zone may be told to evacuate while an adjacent zone stays put. Signals between alarm zones must not overlap, and the whole building uses one common Evacuate signal and one common Alert signal throughout. Alarm zone boundaries must line up with fire detection zone boundaries — a detection zone cannot straddle two alarm zones, though one alarm zone can contain more than one detection zone (clause 13).
A detection zone tells the panel where a fire is; an alarm zone decides which sounders go off together. Alarm zones are separated by proper fire-resisting walls, since one zone might be evacuating while the zone next door is not. The whole building uses the same Evacuate sound and the same Alert sound everywhere. A detection zone always fits entirely inside one alarm zone, never split across two.
No more than 45 m along the route someone would walk. At design stage, when the layout is not known, use 30 m in a straight line. The reduced 25 m and 16 m distances in the 2017 edition were removed in 2025 (clause 19.5).
Nobody should have to walk more than 45 m to a break glass unit. If you are designing before the layout is fixed, use 30 m in a straight line.
No more than 45 m along the route walked. At design stage, when the layout is not known, use 30 m in a straight line.
1.4 m to the centre of the break glass, with a tolerance of 200 mm above and 300 mm below, so 1.1 m to 1.6 m (clause 19.8). Transparent hinged covers are recommended.
Fix them about 1.4 m from the floor. Anywhere from 1.1 m to 1.6 m is acceptable. A clear hinged cover is recommended.
1.4 m to the centre of the break glass, with 200 mm above and 300 mm below allowed: 1.1 m to 1.6 m.
Yes. Every manual call point in a system should use the same Type A method of operation (BS EN 54-11), unless there is a specific reason to differentiate (clause 19.1). A mix of operating styles — some needing a frangible element broken, others a resettable flap — is a recognised nonconformity on an existing system (clause 44.1.2b).
All the break-glass units in a building should work the same way, unless there is a good reason for one to be different. A mix of different styles is flagged as a fault on an existing system.
Within 3 s, in at least the alarm zone containing that call point (clause 19.3). A delay of up to 10 s may be accepted, but only as a recorded variation on the design certificate, agreed with the enforcing authority.
The alarm should sound within 3 seconds of someone breaking the glass, at least in that area. A longer delay, up to 10 seconds, can only be used as an agreed, written-down exception.
In multi-storey buildings with phased evacuation, or where exits from more than one zone lead to the same stairway, call points are sited within the accommodation, not on the stairway landings themselves — because someone walking down past a landing several floors from the fire could trigger evacuation of the wrong areas (clause 19.4 note). Where specific high-hazard equipment or activity is present, such as a kitchen or a spray booth, a call point is also sited close by (clause 19.6).
In buildings with phased evacuation, or where more than one zone's exit uses the same stairway, call points go inside the accommodation rather than on the stairway landings — otherwise someone passing a landing floors away from the fire could set off evacuation in the wrong place. A call point also goes right next to anything especially high-risk, like a kitchen or a spray booth.
L1 has detection throughout. L2 has defined areas plus the L3 areas. L3 covers escape routes and the rooms off them. L4 covers escape routes only. L5 is designed to a specific fire risk objective. M is manual call points only. P1 has detection throughout and P2 in defined areas, both to protect property. Add /M to P1, P2 or L5 for call points.
L is for life, P is for property, and M is call points only. The number says how much of the building has detectors: L1 all of it, L2 some areas plus the escape routes, L3 the escape routes and rooms off them, L4 just the escape routes.
Each plan has a corridor (the escape route), two rooms that open onto it, and two areas behind them. L is for life, P is for property, and M is call points only.
Category L2 now includes rooms where people sleep. The standard now recommends smoke, multi-sensor or CO detectors there, and heat detectors only if a fire risk assessment justifies them. The same applies to sleeping rooms in L3. It is not retrospective.
Rooms where people sleep are now covered by L2. Use smoke, multi-sensor or CO detectors there. Heat detectors need a risk assessment to justify them. Old systems do not have to change.
Pick the lowest category that still protects people, working up: L4 covers escape routes only, suitable where people would notice smoke before it blocks their escape. L3 adds detectors in rooms that open onto those escape routes, because hot gas through a door crack can smoke-log a corridor before a corridor-only detector reacts. L2 adds further high-risk rooms and any room where people sleep — sleeping rooms need smoke, multi-sensor or CO detection, not heat. L1 covers every area, and suits buildings with occupants at special risk, such as hospitals or care homes, or where structural fire precautions are below the usual standard. The same logic applies to property protection: P2 covers only the higher-risk rooms, P1 covers everything (Commentary on Clause 7).
Work up from the minimum: L4 is just the escape routes. L3 adds the rooms that open onto them. L2 adds other risky rooms and anywhere people sleep. L1 covers the whole building, for places like hospitals or care homes where people are most at risk. The same idea applies to property-only systems, between P2 (just the risky rooms) and P1 (everywhere).
Annex A gives typical, not mandatory, categories: hospitals are normally L1 (with possible minor variations); prisons are normally L3; covered shopping centres are typically L1 to L3, often as part of a fire engineering solution; schools often use M/P2 combined with L4 or L5 for areas used outside school hours. The final decision always rests with the enforcing authorities and a proper fire risk assessment for that specific building — Annex A is informative guidance, not a rule to apply automatically.
There is a general-guidance table (Annex A) for typical categories by building type — hospitals and similar high-risk buildings are usually L1, prisons L3, shopping centres L1 to L3. But it is only a starting point: the actual category for a specific building is decided by the enforcing authority and a fire risk assessment, not read straight off the table.
Annex A's table did not extract cleanly from the source PDF; the rows above are the clearest, unambiguous ones. Check the full table in the standard for any premises type not listed here.
About every 6 months. A visit any time between 5 and 7 months after the previous one is acceptable (clause 43.2.1). The 2017 edition said the period should not exceed six months, and a late visit meant the system was no longer compliant.
Service it about every six months. A visit anywhere from 5 to 7 months after the last one is fine.
Service about every 6 months. A visit between 5 and 7 months after the last one is fine.
The panel clock is checked and adjusted at every visit, and alarm receiving centre signals are checked, confirming each signal where more than one can be sent. At the 12-month visit the zone identification on the panel is compared with the zone plan.
At every visit, check the panel clock, and test the signals to the monitoring centre. Once a year, check that the zone names on the panel match the zone plan.
Where a third party maintains the system, there should be a 24-hour call-out agreement under which a technician can normally attend within 8 hours of being called (clause 44.2.1). The maintenance company's name and phone number should be displayed prominently at the main panel (clause 44.2.2), and every fault or piece of damage is logged, with repairs arranged as soon as possible (clause 44.2.3). A fault indication should never be hidden or suppressed just because it cannot be fixed on the spot (clause 44.2.4).
Your maintenance company should normally be able to get an engineer to site within 8 hours of being called, any time, day or night. Their name and number should be on display at the panel, every fault gets logged, and a fault light should never just be switched off to hide it.
Inspect the system and study whatever records exist, and flag any major nonconformity to the premises management — at minimum: too few call points for Clause 19, inconsistent call point operation, inadequate detection for the system's category, heat detectors in bedrooms, sound levels below Clause 15, a missing or inadequate standby supply, cabling that does not meet the fire-resistance recommendations, circuits not properly fault-monitored, poor system integrity, electrical safety shortfalls, a history of false alarms, building changes that affect the system, no zone plan, no zonal indication at the panel, and, in residential care, no automatic ARC link. If there is no logbook, provide one (clause 44.1).
When you take on an existing system, inspect it and check whatever records exist, and flag anything seriously wrong to the building's management — things like too few call points, mismatched call point types, heat detectors in bedrooms, sound levels that do not meet the standard, a missing standby battery, non-fire-rated cable, poor fault monitoring, a history of false alarms, building changes the system has not kept up with, or no zone plan. If there is no logbook, start one.
All detectors and manual call points are functionally tested over each 12-month period, which can be split across two or more service visits (clause 43.3.1).
Over a year every detector and call point should have been tested. Most engineers split it across the two visits.
The user operates one manual call point each week, using a different one each time so all are tested in rotation, and records the result and which call point was used in the log book (clauses 42.1.2 and 42.1.6). There is no maximum rotation period — a building with 150 call points simply takes 150 weeks to cycle through them all.
Once a week someone sets off a different break glass unit to prove the alarm works, and writes down which one and what happened. It doesn't matter how long it takes to get through them all.
Events, faults, false alarms, tests and disablements, and every variation from the standard that has been agreed. In the 2025 edition all variations must be recorded.
Write down every event, fault, false alarm, test and switch-off, and every agreed departure from the standard.
A departure from a recommendation in the standard, agreed with the person responsible and recorded, usually because following it exactly is not practical or does not suit the building. Some variations, such as leaving out a zone plan, are no longer acceptable in 2025.
A variation is an agreed exception to the standard, written down. Some exceptions are no longer allowed.
Annex E: Cmin = 1.25 × (T1 × I1 + D × I2 × T2), in amp hours at the 20-hour rate and 20 °C. 1.25 is the ageing factor and D is the de-rating factor, 1.75 unless the maker gives another figure. The usual defaults are 24 hours standby and 30 minutes alarm. The result is the same as under the 2017 method.
Work out the charge used in standby and in alarm, allow extra for the battery losing capacity with age, and choose the next size up. Use 24 hours standby and 30 minutes alarm unless told otherwise.
Worked example: 0.25 A standby for 24 hours, 0.75 A for 30 minutes of alarm, 25% added for ageing, then the next size up.
For most Category M/L buildings: 24 hours standby, then a 30-minute 'Evacuate' signal in every alarm zone (clause 24.3.5a) — unless there is an automatically started standby generator, in which case 6 hours is enough (24.3.5b). For Category P systems: 24 hours beyond the longest time the premises are likely to be unoccupied, or 72 hours in total, whichever is less, then 30 minutes of alarm (24.3.5c) — this can drop to 24 hours total if the building is staffed, or a power fault is reported automatically to an ARC (24.3.5d).
Most systems need 24 hours of standby power plus 30 minutes of alarm at the end of it. A backup generator can bring that down to 6 hours. Property-only (P) systems need longer standby — enough to cover how long the building might sit empty, up to 72 hours — unless it is staffed or reports power faults to a monitoring centre.
A rechargeable secondary battery with an automatic charger, rated for at least 4 years' life under the conditions it will see in service. Automotive (engine-starting) batteries should not be used (clauses 24.3.1 to 24.3.2). The charger should be able to recharge a correctly sized battery to its full recommended capacity within 24 hours (clause 24.3.4).
Use a proper rechargeable standby battery rated for at least 4 years, never a car battery. The charger should be able to fully recharge it within 24 hours.
Annex G holds the model certificates: design, installation, commissioning, acceptance, verification, inspection and servicing, and extension or modification. A firmware update counts as a modification.
There is a certificate for each stage: design, installation, commissioning, handover acceptance, verification, each service visit, and any extension or change.
An extension of an existing system must itself conform to the current standard, even if the system as a whole still does not (clause 45.1), and responsibility rests with someone competent in fire alarm design, not just installation (clause 45.2). The extended work is recommissioned to the extent needed to check its effect on the existing system — battery capacity, radio signal strength, cause-and-effect — and a signed extensions/modifications certificate is issued (clauses 45.3 to 45.4). A modification, which includes a firmware update to the panel, is treated the same way, since even a small change can introduce errors elsewhere in the system (clause 46 commentary).
New work added to an existing system has to meet the current standard on its own, even if the rest of the system is older, and whoever does it needs real design knowledge, not just installation skills. It gets tested afterwards and signed off with its own certificate. The same applies to a modification — even a software update to the panel — because a small change can have knock-on effects elsewhere.
Heat detectors should not be used on escape routes in Category L systems, in sleeping accommodation, where a small or smouldering fire could cause unacceptable damage in a Category P area, or anywhere they would have a high false-alarm potential (clause 20.2). Smoke detectors should not be used where the main fire hazard is a flammable liquid or gas that produces little smoke, or where they would have a high false-alarm potential, unless no other detector responds fast enough (clause 20.3). In Category L escape-route corridors and stairways, smoke detectors should be optical type, or optical plus combustion gas, rather than ionisation (clause 20.4).
Do not use heat detectors on escape routes, in bedrooms, or anywhere a small smouldering fire could do real damage. Do not use smoke detectors where the main risk is a flammable liquid or gas that barely smokes, or where they will false-alarm constantly. On escape routes, use optical smoke detectors rather than the older ionisation type.
For early detection of a smouldering fire, use optical smoke, optical beam, aspirating, CO or a suitable multi-sensor detector (clause 20.5). For a fast, clean-burning flaming fire, the preferred choices are a suitable multi-sensor or a flame detector, with ionisation smoke detectors or sensitive heat detectors as fallbacks (clause 20.6). A flame detector needs a clear line of sight to the area it protects, and only suits fires that actually produce flame, not pure smoulder (clause 20.8). CO detectors are limited to areas where a heat detector would otherwise be acceptable, escape routes (only alongside a smoke detector), or other areas where the specific fire hazard suits CO detection (clause 20.7).
A smouldering fire is best caught by optical smoke, beam, aspirating, CO or multi-sensor detectors. A fast flaming fire is better caught by a multi-sensor or flame detector — flame detectors need a clear view of the area and only work on fires with visible flame. CO detectors have a narrower role: areas where a heat detector would do, or alongside a smoke detector on an escape route.
A void of 800 mm or more in height generally needs its own detection (clause 21.1.4). Within a void that needs it, the detector sits in the top 125 mm or the top 10%, whichever is greater, up to 1.25 m deep; from 1.25 m to 1.5 m it is the top 10% only; beyond 1.5 m the void is treated as a room, with full room spacing (clause 21.2.7).
A void 800 mm deep or more generally needs its own detectors. How deep it is decides exactly where they go. Past 1.5 m, it is treated like a room.
The deeper the void, the more it needs detection. A very deep void is treated as a room.
A duct smoke detector or sampling probe should sit in a straight run of ductwork, at least three times the duct's width downstream of the nearest bend, corner or junction (clause 21.9.2), with the probe sized and positioned to the manufacturer's guidance to cover as much of the duct's cross-section as possible (clause 21.9.4).
Fit duct detectors in a straight section of ducting, well clear of any bend or junction — at least three duct-widths downstream — and follow the maker's instructions for where the sampling probe sits.
Except in continuously occupied premises, a Category P system must have automatic transmission to an ARC (clause 14.8). In non-domestic premises in multiple occupation, a Category L system needs it too, unless there is a reliable way for occupants to summon the fire and rescue service themselves whenever the premises are occupied (clause 14.9).
A property-protection (P) system needs a monitored link to an alarm receiving centre unless the building is staffed round the clock. A life-safety (L) system in a multi-occupied building needs one too, unless there is another reliable way for someone to call the fire brigade whenever people are in.
Within 90 seconds for Category L systems and 120 seconds for Category P. A complete transmission failure must show at the receiving centre and on the panel within 3 minutes for L, or 31 minutes for P.
The signal must arrive at the monitoring centre within 90 seconds (L) or 120 seconds (P). If the link fails completely, it must be noticed within 3 minutes (L) or 31 minutes (P).
Two clocks: how fast an alarm gets through, and how fast a broken link is noticed. The two bars use different scales.
A false alarm notice at or beside the panel, so people warn the receiving centre before a test. The centre should also be given premises information, such as whether people sleep there and, where practicable, the device type and whether coincidence filtering is used.
Put a label at the panel reminding people to tell the monitoring centre before testing. Tell the centre about the building, for example whether people sleep there.
All fire alarm cables and the low-voltage mains feed should be fire-resistant to the same grade, in one common colour, with red preferred. Black or white should not be used. 'Standard' fire-resistant cable means PH30 (BS EN 50200 with the Annex E water-spray test, 30 minutes) and 'enhanced' means PH120 (BS EN 50200 plus BS 8434-2, 120 minutes). Cable that is not fire-resistant but is mechanically protected no longer complies.
Use fire-resistant cable throughout, one colour, preferably red. Standard means 30 minutes of fire resistance and enhanced means 120 minutes. Ordinary cable in protection no longer counts.
Fire-resistant cable throughout, one colour, red preferred. PH30 is standard and PH120 is enhanced.
Yes. Fire alarm circuits are segregated from other services' cables to stop another circuit's insulation breakdown, a fire on another circuit, electromagnetic interference, or work on nearby trunking from affecting the fire alarm. Where fire alarm cable carries more than ELV, it must be segregated from the system's own ELV circuits too, following the manufacturer's separation guidance, and a mains supply cable should not enter equipment through the same cable entry as an ELV cable (clause 25 commentary, clauses 35.8 to 35.9).
Yes — fire alarm wiring is kept apart from other building wiring, so a fault, fire or interference on another circuit cannot take down the fire alarm. Within the fire alarm system itself, mains-voltage cable is kept apart from the low-voltage (ELV) wiring too, including using separate cable entries into equipment.
Keep fire alarm cables separated from high-current power cables wherever practicable, especially ones feeding inductive loads, and avoid more than around 35 m in total running close alongside them. Where the two have to cross, cross at right angles rather than running in parallel. Cable screens need proper termination — the full 360° of the screen for mineral-insulated cable, or continued to the right terminal for other types — with exposed core kept to a minimum (clause 27 commentary, clauses 27.4, 27.7 to 27.9).
Keep fire alarm cable away from high-current power cables where you can, especially ones feeding motors or similar. If they have to cross, cross them at a right angle, not running alongside each other. Make sure cable screens are properly terminated all the way round, not just twisted off.
The system should meet BS 7671 generally, with the functional earth (FE) conductor identified by pink insulation or sleeving, or marked 'FE', per BS 7671 Table 51 (clauses 28.1 to 28.2). Where removing a detector or similar exposes ELV parts to touch, the power supply needs to be treated as a SELV installation, and in higher-shock-risk locations — bathrooms, pools, saunas, medical areas — extra conditions apply: very low circuit voltage, a special tool needed to expose the parts, or the parts being out of reach of anyone but authorised maintenance staff (clause 28.5).
Fire alarm earthing follows the normal wiring regs, with the functional earth wire marked pink or labelled 'FE'. Where pulling off a detector exposes live-feeling parts, the power supply has to be treated as extra-low-voltage-safe, and in riskier spots like bathrooms or pools there are extra conditions — very low voltage, a special tool to get at the parts, or the parts simply being out of normal reach.
Tested at 500 V DC, with equipment disconnected, the insulation resistance between conductors, each conductor and earth, and each conductor and any screen should be at least 2 MΩ (clause 36.1). Earth continuity, and earth fault loop impedance on mains circuits, should meet BS 7671 (clause 36.2). Where the manufacturer specifies a maximum circuit resistance, that is measured too, and the results are recorded and handed to whoever commissions the system (clauses 36.3 to 36.4).
New fire alarm cabling is tested at 500 V DC, with equipment disconnected, and should read at least 2 MΩ between conductors, each conductor and earth, and each conductor and any screen. Earth continuity follows the normal wiring regs. Write the results down and pass them to whoever commissions the system.
Not unless BS 7671 requires one for electrical safety. Where an RCD is necessary, it must be arranged so that a fault on any other circuit or piece of equipment in the building cannot trip the fire alarm's own supply (clause 24.1.10).
Avoid putting the fire alarm on an RCD unless the wiring regs actually require one. If it has to have one, a fault anywhere else in the building must not be able to take out the fire alarm's power.
Any isolator, switch or protective device that can disconnect the mains supply should be sited where unauthorised people cannot reach it, or protected against unauthorised operation by a special tool — ordinary slot-headed screws do not count (clause 24.1.9). Labels should be clear and fade-resistant (clause 24.1.8). Whatever the state of the standby battery — even disconnected or flat — the mains supply alone must still be able to carry the system's maximum alarm load (clause 24.1.11).
The mains isolator should be somewhere the public cannot get at it, or need a proper tool to operate, with a clear, durable label. The mains supply on its own, battery or no battery, has to be able to run the system at full alarm.
Every radio-linked component needs at least two independent power sources — mains plus a reserve battery, or two separate batteries (clause 26.2a). A fault is signalled at the panel once any component's remaining power can no longer keep it running for 30 days, plus 30 minutes in the alarm condition for a fire alarm device (clause 26.2b).
Every wireless device needs two separate power sources — mains and a backup battery, or two batteries. The panel shows a fault once a device's power is down to its last 30 days (plus 30 minutes at alarm), not when it is actually dead.
A full radio survey first, checking for interference, confirming adequate signal strength everywhere a radio-linked component will sit, and, on a networked system, across the whole network (clause 26.7), using the manufacturer's approved, calibrated survey equipment (clause 26.8). The signal levels, the background noise, and the system's own address/channel details are recorded at commissioning and kept on site (clauses 26.9 to 26.12). On a networked system, the signal levels between panels are then checked again every 12 months (clause 26.10).
Before fitting a wireless system, survey the building for radio interference and check signal strength everywhere a device will go, using proper calibrated survey kit. Keep a record of the signal levels and the system's settings on site, and on a multi-panel system, re-check the signal between panels every year.
Yes. BS 5839-1:2025 (clause 24.3.3) recommends marking batteries with their installation date. Writing it on the casing in permanent marker is acceptable.
Write the date the battery was fitted on the battery, in permanent marker.
Required wherever ambient noise exceeds 90 dB(A), or anywhere hearing protection is normally worn (clause 16.1). Separately, they are also used to warn people who are Deaf or have a hearing impairment, for example someone who may be alone in a toilet or plant room (Clause 17 commentary). They should conform to BS EN 54-23, be mounted at least 2.1 m high (clause 16.5), and use Category W (wall) or C (ceiling) devices for ordinary rooms — Category O is reserved for a specific, engineered design (clause 16.4). A visual alarm device on its own will not wake a sleeping person.
Flashing beacons are required in noisy areas (over 90 dB(A)) or anywhere hearing protection is normally worn. They are also used, separately, to warn deaf or hard-of-hearing people, for example in a toilet or plant room where someone might be alone. Fit certified ones at least 2.1 m up. A flashing light on its own will not wake someone who is asleep.
A visual alarm device only counts as a fire alarm device under this standard if its circuit is monitored and protected like any other device. One that is not monitored this way can only supplement a properly monitored device — it cannot be the primary way of giving the alarm (clause 17.1.1).
A flashing beacon only properly counts as part of the fire alarm system if its wiring is watched for faults the same as everything else. A beacon that is not monitored this way can only ever be an extra, not the main warning.
All sounders in a building should have similar sound characteristics, unless that is impractical in a particular area, and the fire alarm sound should be distinct from any other alarm in the building (clause 15.1.5). If one sounder circuit develops an open circuit or short circuit, at least one sounder near the panel must still operate (clause 11.2.9). A second, independent sounder circuit is specifically required for large public spaces: an uncompartmented space over 4,000 m², or one built for more than 500 people (clause 11.2.10).
Sounders across a building should all sound the same, except where that is not practical, and should sound different from any other alarm in the building. If a circuit fails, at least one sounder near the panel must still work. A second, separate circuit is only specifically required for big public spaces — over 4,000 m² or built for 500 or more people.
Yes. The same sounder may carry non-fire signals using different tones. School class-change signals may last up to 10 seconds (it was 5). Remote indicators must show red and are checked at the annual service.
A fire sounder can also give other signals if the tone is different. School bells can be 10 seconds long. Remote indicators must be red and are checked each year.
A staged alarm gives a different signal to different areas: an 'Alert' signal warns an area not yet affected that evacuation may follow, while 'Evacuate' means leave now — used for phased evacuation in large or high-rise buildings, or where a staff alarm investigates before a general signal is given (clause 18 commentary). Where phased evacuation is used because stairway capacity cannot take everyone at once, no single control may give an 'Evacuate' signal to the whole building — each alarm zone needs its own Evacuate control (clause 18.1).
In some buildings the alarm has two signals: 'Alert' (be ready) and 'Evacuate' (leave now), so people are not all sent down the same stairs at once. Where that is the reason for staging, there is deliberately no single button that evacuates the whole building at once — each zone has its own.
A clearly labelled evacuate control must be provided at or next to the panel, separate in function from the sounder silence/resound controls, and it must work regardless of whether anything else is silenced or disabled (clause 22.3.2). Where the building has two or more alarm zones, each part needing simultaneous evacuation normally gets its own evacuate control — and in a phased-evacuation building where the stairways cannot take everyone at once, there must be no single control that evacuates every zone at the same time (clause 22.3.3). Controls like this, along with disablement controls, are restricted to authorised personnel, by a key switch or by physically limiting who can reach the panel (clause 22.3.4).
The panel needs its own clearly labelled evacuate button, separate from silence and reset, that always works no matter what else is switched off. In a building with several alarm zones, each zone that needs its own evacuation gets its own button — and in a phased-evacuation building, there must be no single button that evacuates everyone at once. These controls, and disablement, are locked to authorised staff only.
Two. Leaving out a zone plan where a storey has more than one zone, and having no alarm receiving centre link in residential care or supported housing that needs Grade A.
You cannot agree to skip a zone plan on a floor with several zones, or skip the monitoring link in care homes that need a full system.
A cause-and-effect matrix or a plain-text description of what should happen, the detector type and settings chosen for multi-sensors, the zone plan and the log book, which may be digital or paper. Redundant devices are removed or labelled 'not in use'.
Hand over a description of what triggers what, the multi-sensor settings, the zone plan and the log book. Old devices should be taken out or marked as not in use.
Design, installation and commissioning certificates; an operation and maintenance manual covering the detector types chosen, how to use the controls, and what to do after a false alarm or a real fire; as-fitted drawings showing where everything is and the actual cable routes — a simple wiring-sequence schematic is not enough, except on small, simple systems; a cause-and-effect matrix or description; a logbook; and a record of any agreed variations (clause 38.1).
You should get: certificates for design, installation and commissioning; a manual covering the detectors fitted, how to use the controls, and what to do after a false alarm or fire; proper as-fitted drawings showing where everything actually is and how the cables actually run, not just a wiring diagram; a cause-and-effect description; a logbook; and a note of any agreed exceptions to the standard.
At every panel and at any repeat indicator, there should be a diagrammatic representation of the building — an illuminated mimic diagram, a VDU, or a printed, correctly orientated zone plan (clause 22.2.5). A plain list of zone numbers does not satisfy this.
Put a zone plan, or an equivalent picture display, by the panel and each repeat panel. A list of zone numbers on its own is not enough.
On a system with more than 50 automatic fire detectors, the designer sets a soak period of at least one week after commissioning, with any ARC connection disabled and every call point labelled as not for use. The system is not treated as the real means of warning of fire until that soak test passes — which it does only if no false alarm occurred, or every false alarm that did occur was investigated and explained, with the cause addressed (clause 33.5).
On a bigger system (more than 50 detectors), there is a settling-in period of at least a week after commissioning before it is trusted as the real fire alarm — the monitoring link is switched off and call points are labelled not for use. It only passes if nothing false-alarmed, or every false alarm that did happen was properly explained and sorted.
Four categories: unwanted alarms, where the system responds as it reasonably would to something fire-like — smoke from a bonfire, dust, accidental damage, or someone testing without warning anyone first; equipment false alarms, an actual fault in the system; malicious false alarms, someone deliberately setting it off, knowing there is no fire; and false alarms with good intent, someone sincerely, if wrongly, believing there is a fire (clause 30 commentary). Most false alarms are unwanted alarms, not equipment faults — a common misconception.
There are four kinds: the system reacting to something fire-like, such as smoke, dust, damage or an untested test — this is most of them; an actual fault in the equipment; someone setting it off on purpose; and someone mistakenly thinking there is a fire. People often assume it is usually a faulty detector — it usually is not.
The user should investigate every false alarm (clause 31.2). At every service visit the engineer also checks the false alarm record and works out the rate: 100 × (false alarms ÷ number of automatic detectors) over the previous 12 months (Annex F). A preliminary investigation is required if that exceeds 4 false alarms per 100 detectors a year, or if more than 10 false alarms have happened since the last visit (clauses 31.1 to 31.2).
Whoever looks after the building should look into every false alarm. The engineer also works out a false-alarm rate at each service visit, and a high rate — or more than 10 false alarms since the last visit — triggers a proper investigation.
Someone with the training, knowledge and experience to do the work, who keeps that competence up, probably through continuing professional development. The designer signs a design certificate and ideally witnesses testing.
Someone who has the training and experience for the job and keeps their skills up to date.
Commissioning is carried out by someone with at least a basic working knowledge of the design (Section 2), false alarm limitation (Section 3) and installation (Section 4) recommendations, who has access to the system specification. The commissioning technician's job is to verify the system works as designed and that the installation is sound — not, generally, to re-verify that the design itself conforms to the standard — though in practice commissioning is often the first real opportunity to check things like whether sound levels actually meet Clause 15 in the finished building (clause 37 commentary, clauses 37.1 to 37.3).
Whoever commissions the system needs a working knowledge of design, false-alarm prevention and installation practice, and the original specification to work from. Their job is to check the system works as designed and was installed properly — not to redo the whole design check — though in practice commissioning is often the first real chance to confirm things like sound levels actually work in the finished building.
Verification is an optional extra check, usually used on large or complex systems, or where design information evolved during the build. The purchaser or user can ask anyone competent — the designer, supplier, or an independent third party — to verify conformity to the standard, with the scope agreed between them in advance. A verification certificate is then issued, stating what was and was not covered (clause 41).
Verification is an optional, separate check that the system really does meet the standard — not mandatory, but often asked for on big or complicated jobs, or where the design changed a lot during the build. Whoever does it agrees the scope first, then issues a verification certificate saying exactly what they checked.
Keep it to a practical minimum, and tell premises management (or their representative) which areas are affected (clause 43.2.18). Protection must be fully reinstated once the work is finished.
Switch off as little as possible, and tell the building manager which parts are off. Everything must be properly switched back on once the work is done.
Any facility provided for deliberately disabling call points or detectors should let one zone be disabled without affecting protection in any other zone, and must not stop the evacuate control at or near the panel from working (clause 11.2.6).
A proper disablement facility lets you switch off one zone on its own, without touching any other zone, and it must never get in the way of the evacuate button at the panel.
A single open-circuit or short-circuit fault must not disable detection over more than 2,000 m², or across more than one floor plus a maximum of five devices on the floor above and five below (clause 11.2.2). Two simultaneous faults on a call point or detector circuit must not disable more than 10,000 m² (clause 11.2.3). A fault on one circuit must never affect another circuit at all (clause 11.2.1).
One single fault on a circuit should never be able to knock out more than 2,000 m² of detection, or spread beyond one floor, apart from up to 5 devices each on the floor above and below. Two faults at once should never knock out more than 10,000 m². And a fault on one circuit should never spread to a different circuit at all.
Removing a detector, or all of them, from its base must never stop a manual call point on the same circuit from working (clause 11.2.5a). If malicious removal is a realistic risk, use detectors that only come off with a special tool, not something the general public would carry (clause 11.2.5b). Separately, a software-controlled panel with more than 512 detectors and/or call points connected needs to follow the manufacturer's own instructions for meeting BS EN 54-2 (clause 11.2.4).
Pulling a detector off its base — even every detector in the system — must never stop the call points working. If someone might deliberately pull detectors off, use ones that need a special tool to remove, not something anyone could carry. A big addressable panel, over 512 devices, follows the maker's own instructions for staying compliant.
Duct-mounted smoke detectors are tested. The zone shown on the panel is checked against the zone tested and the zone plan. Every detector, call point and sounder is tested within the year, and remote indicators are checked for obstruction or paint.
Once a year also test detectors in air ducts, and check that the zone names on the panel, the plan and what you tested all agree.
Lock communications cabinets, use anti-tamper patch plugs, and authenticate before any remote connection. A risk assessment is needed before remote read, control or write access.
Keep network cabinets locked, use tamper-proof plugs, and make people prove who they are before connecting remotely. Assess the risk before allowing remote changes.
A networked system — several sub-panels linked by a network rather than one central panel — must overall be as reliable as a single-panel system and meet every other recommendation in the standard. If the cause-and-effect logic depends on the network link, that link is treated as a critical signal path: monitored for faults, wired in suitable cable, and able to get a manual call point's signal to other alarm zones within 10 seconds (the 3-second response within the zone of origin is unchanged). Ring or loop networks cope with a communications failure better than radial ones (clause 23 commentary).
A system built from several linked panels instead of one has to be just as reliable as a single-panel system. If the panels depend on each other to work properly, that link between them needs the same fault-monitoring and fire-resistant cable as everything else, and a call point in one zone still needs to reach other zones within 10 seconds. Ring or loop wiring between panels copes with a fault better than a simple radial link.
Any part of the system in, or with cables passing through, an area where an explosive gas, vapour, mist or dust atmosphere could occur should be installed to BS EN 60079-14 and maintained to BS EN IEC 60079-17 (clauses 9.1 to 9.2). The FIA's ATEX equipment guide gives further practical detail.
In any area where an explosive atmosphere is possible — flammable gas, vapour or dust — the fire alarm equipment and wiring there needs special ATEX-rated installation and maintenance, not standard practice.
Yes — actuating things like automatic extinguishing systems, fire doors, air handling shutdown or lift grounding should meet the relevant part of BS 7273 (clause 8.2). If testing the fire alarm could set these off unintentionally, there should be a way to disable just that automatic actuation, built and indicated to BS EN 54-2 (clause 8.3). Other systems should not draw power from the fire alarm system's own supply where this can be avoided (clause 8.4), and any interface must stay accessible for maintenance (clause 8.5).
Yes, but it has to follow BS 7273 for whatever it is triggering (sprinklers, door releases, shutting down air handling, grounding lifts). There needs to be a way to disable just that triggering during testing, without disabling the fire alarm itself, and other equipment should not be powered from the fire alarm's own supply.
If the gap above it is under 300 mm and its depth is more than 10% of the ceiling height. Keep detectors at least twice the depth away from an isolated obstruction up to 250 mm deep. Closely spaced beams are about 1 m apart or less.
A deep beam or partition close to the ceiling counts as a wall. Keep detectors well away from shallow obstructions, at least twice their depth.
A beam counts as a wall if the gap above it is under 300 mm and it is deeper than 10% of the ceiling height.
From Table 3 (clause 21.8): optical beam detectors reach a 25 m ceiling at normal sensitivity (28 m over up to 10% of the area), or 40 m at enhanced sensitivity — alarm at 35% attenuation or less (43 m for 10%). Aspirating detection reaches 10.5 m/12.5 m as a general limit, 15 m/18 m with Class C and at least 5 sampling holes, 25 m/28 m with Class C and at least 15 holes, and 40 m/43 m with Class B and at least 15 holes. Linear heat cable uses BS EN 54-22 (resettable) or 54-28 (non-resettable).
Beam detectors reach higher ceilings than ordinary point detectors — 25 m at normal sensitivity, 40 m with the more sensitive type. Aspirating (sampling-pipe) systems can also reach up to 40 m, with the right class of detector and enough sampling holes.
Line heat detectors follow the same wall, void and obstruction rules as point heat detectors, with two extra points: a section running within 500 mm of a wall or obstruction is discounted from providing detection, except where that section is within 500 mm of the detector's own control equipment (clause 21.5.15); and where the detector protects a specific item of plant or cabling rather than a general area, it is mounted as close as possible to where fire or overheating could occur, either above the risk or in thermal contact with it (clause 21.5.16).
Line heat detectors follow the usual wall and obstruction rules, with two extras: any run within 500 mm of a wall or obstruction does not count as covering anything there (except near its own control gear), and when it is protecting a specific piece of plant or cable rather than a whole area, it should sit as close as possible to where overheating would actually start.
An enclosed stairway has a detector at the top and on each main landing (clause 21.1.2). A shaft or flue-like structure — for a lift, escalator, hoist or chute — that penetrates a ceiling has a detector at the top, and, for the fuller system categories (L1 to L3, P1), also on each level within about 1.5 m of the penetration (clause 21.1.3). Stairways and shafts are separate zones.
On an enclosed staircase, a detector at the top and on each main landing. Lift shafts and similar get one at the top, plus one per floor on the better-protected system categories.
Enclosed stairs: a detector at the top and on each main landing. Open stairs, shafts and risers: one within 1.5 m of the opening.